Digital Integration Laboratory (DIL)

Created: 4/1/2014
Contract Vehicle:
STOC II
RFP Number:
STOCII-14-KOP-003
Proposed Issue Date:
9/21/2014
Type of Acquisition:
STOC II: Competitive - Lot I Full & Open
Contract Specialist:
Bushway, Jackie
Contracting Officer:
Brief Summary:

This DRAFT RFP has been updated to include Questions and Answers received in response to the DRAFT RFP.The anticipatedRFP release date will be June 2014 instead of May 2014. As a result of this update, the following document has been included:

- Enc 11 - DIL Draft RPF Q-A 20140527

No other changes to the Draft RFP are being made at this time.

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

This is a DRAFT Request for Proposal (RFP) for PM Constructive Simulation’s (PM CONSIM’s) Digital Integration Laboratory (DIL).

Questions and comments regarding the DRAFT Solicitation are welcome and must be submitted no later than 1300 Hrs EST, 15 April 2014. Offerors are encouraged to comment on the clarity of the requirement, the criteria and instructions, the page count limit, and the necessity of a hard copy of the proposal. Please send questions and comments in writing directly to the Contract Specialist, Jackie Bushway, at Jacqueline.Bushway@us.army.mil, with a copy furnished to Aurora Ramirez at Aurora.I.Ramirez@us.army.mil.

The Government will host a site visit of the DIL on Tuesday, April 8, 2014 at 9:30 am. Each prospective offeror is limited to two individuals for the site visit. Names, birth dates, and country of citizenship must be coordinated through Kathleen Bancroft (kathleen.b.bancroft.ctr@us.army.mil, (407) 384-3991), by close of business on Friday, April 4, 2014. The site visit will start promptly at 9:30 am, with a short explanation of the lab; followed by half an hour for the visit. Questions will not be answered at this time. All questions must be submitted in writing to the Contract Specialist. No electronic devices will be allowed in the DIL during this site visit or at any other time, to include cell phones, cameras, laptops, tablets, etc.

This requirement is being competed within STOC II Lot I. A Firm Fixed Price (FFP) task order with Cost provisions is anticipated. The period of performance to include exercised options will not exceed five years.

Anticipated Procurement Acquisition Lead Time (PALT) milestones are as follows:

(All Milestone Event Dates Are Approximate)

Request for Proposal: May 2014

Proposal Submission: June 2014

Target Award Date:December 2014

Proposal preparation time is anticipated to be 30 days.

DISCLAIMER: This notice does not constitute an invitation for bids or an RFP and is not a commitment by the U.S. Government to procure subject services. All documents are subject to change prior to the release of the final RFP and therefore offerors should not rely upon these documents for proposal purposes.