Counter Rocket, Artillery, Mortar (C-RAM) Land Based Phalanx Weapon System (LPWS) Computer Based Training (CBT) System

Created: 2/25/2016
Contract Vehicle:
0
RFP Number:
STOCII-15-KOV-0005
Proposed Issue Date:
3/30/2016
Type of Acquisition:
2
Contract Specialist:
Contracting Officer:
Brief Summary:

UPDATE 17 March 2016:

1. Answers to questions from industry are hereby attached. See document named 'Questions and Answers C-RAM RFP 20160316.'

2. Enclosure 5 has been revised to make correction to CDRL B008. See document named 'Encl 5c, CDRLB008 (updated).'

*******************************************************************

UPDATE 9 March 2016:

1. Enclosure 2 (Section L and M, Proposal Submission and Eval Criteria) has been revised to correct the date provided for the last day to submit questions and the date for proposal submission. Both dates now match with the dates that are indicated in the RFP letter.

2. Enclosure 2 has also been revised to reflect changes made as result of questions from industry.

3. Answers to questions from industry are hereby attached. See document named 'Questions and Answers C-RAM RFP 20160304'

*******************************************************************

The Program Executive Officer for Simulation, Training, and Instrumentation (PEO STRI) has a requirement for LPWS OMT systems to train C-RAM Military Operational Specialists (MOSs) to operate and maintain the C-RAM LPWS system. The period of performance is for FY 17 through FY 18. Award of a Firm Fixed Price delivery order is planned for 24 October 2016.

NAICS: 333319
Size Standard: 500

Proposal Submission Instructions

As provided by Section H.16, Delivery/Task Order Ordering Procedures of the STOC II contract, it is requested that you submit a written proposal in response to Enclosure 1, Statement of Work. Specific proposal instructions and evaluation criteria are included in Enclosure 2, Proposal Submission Instructions and Evaluation Criteria. Questions concerning this RFP or attached documents are required no later than COB 15 March 2016. Questions received after this date may or may not be answered.

Key Milestones

Proposal Submission1400hrs on 30 Mar 2016
Contract Award24 October 2016
Post Award Conference13 November 2016
Period of Performance14 November 2016 - 14 May 2018